Ongoing Projects
  • Project : Eklakhi-Balurghat (Capital)
    Anticipated cost (2015-16) : Rs.703.18 Cr
    Cumulative Expenditure : Rs.258.39 Cr
    Fund alloted (2015-16) : Rs.4 Cr.
    Fund alloted (revised) : Rs.4 Cr.
    Fund alloted (final) : Rs.1.45 Cr.
    Expenditure (2015-16) : Rs.1.44 Cr
    Financial progress during (2015-16) : 99.36%
    Overall financial progress : 36.75%
  • Project : Dimapur - Kohima (Capital)
    Anticipated cost (2015-16) : Rs.2315.3 Cr
    Cumulative Expenditure : Rs.147.52 Cr
    Fund alloted (2015-16) : Rs.300 Cr.
    Fund alloted (revised) : Rs.90 Cr.
    Fund alloted (final) : Rs.87.54 Cr.
    Expenditure (2015-16) : Rs.87.57 Cr
    Financial progress during (2015-16) : 100.03%
    Overall financial progress : 6.37%
  • Project : Agartala-Subroom (Capital)
    Anticipated cost (2015-16) : Rs.1141.75 Cr
    Cumulative Expenditure : Rs.1569.47 Cr
    Fund alloted (2015-16) : Rs.455.48 Cr.
    Fund alloted (revised) : Rs.505 Cr.
    Fund alloted (final) : Rs.545 Cr.
    Expenditure (2015-16) : Rs.545.17 Cr
    Financial progress during (2015-16) : 100.03%
    Overall financial progress : 137.46%
  • Project : Jalalgarh-Kishanganj (Capital)
    Anticipated cost (2015-16) : Rs.359.86 Cr
    Cumulative Expenditure : Rs.3.13 Cr
    Fund alloted (2015-16) : Rs.2 Cr.
    Fund alloted (revised) : Rs.2 Cr.
    Fund alloted (final) : Rs.0.01 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 0.87%
  • Project : Bhairabi-Sairong (Capital)
    Anticipated cost (2015-16) : Rs.2393.48 Cr
    Cumulative Expenditure : Rs.549.89 Cr
    Fund alloted (2015-16) : Rs.450 Cr.
    Fund alloted (revised) : Rs.300 Cr.
    Fund alloted (final) : Rs.305.98 Cr.
    Expenditure (2015-16) : Rs.305.98 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 22.97%
  • Project : Sivok- Rongpo (Capital)
    Anticipated cost (2015-16) : Rs.4084.69 Cr
    Cumulative Expenditure : Rs.383.97 Cr
    Fund alloted (2015-16) : Rs.230 Cr.
    Fund alloted (revised) : Rs.100 Cr.
    Fund alloted (final) : Rs.203.2 Cr.
    Expenditure (2015-16) : Rs.203.18 Cr
    Financial progress during (2015-16) : 99.99%
    Overall financial progress : 9.4%
  • Project : Jogbani - Biratnagar(Nepal) (EBR)
    Anticipated cost (2015-16) : Rs.241.52 Cr
    Cumulative Expenditure : Rs.233.46 Cr
    Fund alloted (2015-16) : Rs.75 Cr.
    Fund alloted (revised) : Rs.75 Cr.
    Fund alloted (final) : Rs.75 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 96.66%
  • Project : Byrnihat - Shillong (Capital)
    Anticipated cost (2015-16) : Rs.4083.02 Cr
    Cumulative Expenditure : Rs.14.8 Cr
    Fund alloted (2015-16) : Rs.10 Cr.
    Fund alloted (revised) : Rs.10 Cr.
    Fund alloted (final) : Rs.4.17 Cr.
    Expenditure (2015-16) : Rs.4.16 Cr
    Financial progress during (2015-16) : 99.79%
    Overall financial progress : 0.36%
  • Project : Kaliyaganj - Buniadpur (Capital)
    Anticipated cost (2015-16) : Rs.222.21 Cr
    Cumulative Expenditure : Rs.27.42 Cr
    Fund alloted (2015-16) : Rs.2 Cr.
    Fund alloted (revised) : Rs.5 Cr.
    Fund alloted (final) : Rs.1.86 Cr.
    Expenditure (2015-16) : Rs.1.86 Cr
    Financial progress during (2015-16) : 99.73%
    Overall financial progress : 12.34%
  • Project : Balurghat - Hilli (Capital)
    Anticipated cost (2015-16) : Rs.242.22 Cr
    Cumulative Expenditure : Rs.45.36 Cr
    Fund alloted (2015-16) : Rs.4 Cr.
    Fund alloted (revised) : Rs.4 Cr.
    Fund alloted (final) : Rs.3.74 Cr.
    Expenditure (2015-16) : Rs.3.73 Cr
    Financial progress during (2015-16) : 99.92%
    Overall financial progress : 18.73%
  • Project : Murkongselek-Pashighat (Capital)
    Anticipated cost (2015-16) : Rs.545.64 Cr
    Cumulative Expenditure : Rs.0.79 Cr
    Fund alloted (2015-16) : Rs.10 Cr.
    Fund alloted (revised) : Rs.2.5 Cr.
    Fund alloted (final) : Rs.0.25 Cr.
    Expenditure (2015-16) : Rs.0.23 Cr
    Financial progress during (2015-16) : 95.1%
    Overall financial progress : 0.15%
  • Project : Dudhnoi-Mendipathar (Capital)
    Anticipated cost (2015-16) : Rs.175.43 Cr
    Cumulative Expenditure : Rs.307.3 Cr
    Fund alloted (2015-16) : Rs.5 Cr.
    Fund alloted (revised) : Rs.45 Cr.
    Fund alloted (final) : Rs.40.78 Cr.
    Expenditure (2015-16) : Rs.40.79 Cr
    Financial progress during (2015-16) : 100.03%
    Overall financial progress : 175.17%
  • Project : Agartala- Akhaura(Bangladesh) (EBR)
    Anticipated cost (2015-16) : Rs.252 Cr
    Cumulative Expenditure : Rs.148.4 Cr
    Fund alloted (2015-16) : Rs.148.4 Cr.
    Fund alloted (revised) : Rs.148.4 Cr.
    Fund alloted (final) : Rs.148.4 Cr.
    Expenditure (2015-16) : Rs.148.4 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 58.89%
  • Project : Dimapur - Tizit (Capital)
    Anticipated cost (2015-16) : Rs.4274 Cr
    Cumulative Expenditure : Rs.0 Cr
    Fund alloted (2015-16) : Rs.10 Cr.
    Fund alloted (revised) : Rs.10 Cr.
    Fund alloted (final) : Rs.0.01 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 0.00%
  • Project : Lumding-Dibrugarh (Capital)
    Anticipated cost (2015-16) : Rs.787.92 Cr
    Cumulative Expenditure : Rs.788.59 Cr
    Fund alloted (2015-16) : Rs.5 Cr.
    Fund alloted (revised) : Rs.6.5 Cr.
    Fund alloted (final) : Rs.0.5 Cr.
    Expenditure (2015-16) : Rs.0.5 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 100.09%
  • Project : Lumding-Silchar (Capital)
    Anticipated cost (2015-16) : Rs.5117.23 Cr
    Cumulative Expenditure : Rs.6020.45 Cr
    Fund alloted (2015-16) : Rs.500 Cr.
    Fund alloted (revised) : Rs.800 Cr.
    Fund alloted (final) : Rs.873.32 Cr.
    Expenditure (2015-16) : Rs.873.25 Cr
    Financial progress during (2015-16) : 99.99%
    Overall financial progress : 117.65%
  • Project : Katihar-Jogbani (Cap )
    Anticipated cost (2015-16) : Rs.744.69 Cr
    Cumulative Expenditure : Rs.458.86 Cr
    Fund alloted (2015-16) : Rs.50 Cr.
    Fund alloted (revised) : Rs.10 Cr.
    Fund alloted (final) : Rs.8.34 Cr.
    Expenditure (2015-16) : Rs.9.32 Cr
    Financial progress during (2015-16) : 111.83%
    Overall financial progress : 61.62%
  • Project : Katakhal-Bhairabi (Cap )
    Anticipated cost (2015-16) : Rs.208.36 Cr
    Cumulative Expenditure : Rs.286.07 Cr
    Fund alloted (2015-16) : Rs.80 Cr.
    Fund alloted (revised) : Rs.80 Cr.
    Fund alloted (final) : Rs.72.4 Cr.
    Expenditure (2015-16) : Rs.72.35 Cr
    Financial progress during (2015-16) : 99.93%
    Overall financial progress : 137.3%
  • Project : New Jalpaiguri-Siliguri-New Bongaigaon (Cap)
    Anticipated cost (2015-16) : Rs.1327.78 Cr
    Cumulative Expenditure : Rs.981.5 Cr
    Fund alloted (2015-16) : Rs.10 Cr.
    Fund alloted (revised) : Rs.25.5 Cr.
    Fund alloted (final) : Rs.23.96 Cr.
    Expenditure (2015-16) : Rs.23.94 Cr
    Financial progress during (2015-16) : 99.92%
    Overall financial progress : 73.92%
  • Project : Rangia - Murkongselek (Cap)
    Anticipated cost (2015-16) : Rs.2985.38 Cr
    Cumulative Expenditure : Rs.4043.91 Cr
    Fund alloted (2015-16) : Rs.300 Cr.
    Fund alloted (revised) : Rs.500 Cr.
    Fund alloted (final) : Rs.506.4 Cr.
    Expenditure (2015-16) : Rs.506.4 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 135.46%
  • Project : Aluabari - Siliguri (Cap)
    Anticipated cost (2015-16) : Rs.485 Cr
    Cumulative Expenditure : Rs.435.24 Cr
    Fund alloted (2015-16) : Rs.10 Cr.
    Fund alloted (revised) : Rs.10 Cr.
    Fund alloted (final) : Rs.10.97 Cr.
    Expenditure (2015-16) : Rs.10.67 Cr
    Financial progress during (2015-16) : 97.3%
    Overall financial progress : 89.74%
  • Project : Lumding -Hojai Patch Doubling (Cap)
    Anticipated cost (2015-16) : Rs.0.3 Cr
    Cumulative Expenditure : Rs.0.3 Cr
    Fund alloted (2015-16) : Rs.50 Cr.
    Fund alloted (revised) : Rs.0.5 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 100%
  • Project : Kumarghat-Agartala (Capital)
    Anticipated cost (2015-16) : Rs.1091.98 Cr
    Cumulative Expenditure : Rs.1194.52 Cr
    Fund alloted (2015-16) : Rs.111 Cr.
    Fund alloted (revised) : Rs.155 Cr.
    Fund alloted (final) : Rs.157.22 Cr.
    Expenditure (2015-16) : Rs.157.2 Cr
    Financial progress during (2015-16) : 99.99%
    Overall financial progress : 109.39%
  • Project : New Guwahati - Digaru (Cap. Fund)
    Anticipated cost (2015-16) : Rs.37.5 Cr
    Cumulative Expenditure : Rs.37.5 Cr
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 100%
  • Project : Ambari Falakata-New Mainaguri (Cap)
    Anticipated cost (2015-16) : Rs.171 Cr
    Cumulative Expenditure : Rs.171 Cr
    Fund alloted (2015-16) : Rs.150 Cr.
    Fund alloted (revised) : Rs.0.01 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 100%
  • Project : New Coochbehar - Samuktala Road (Cap)
    Anticipated cost (2015-16) : Rs.133.96 Cr
    Cumulative Expenditure : Rs.133.96 Cr
    Fund alloted (2015-16) : Rs.195 Cr.
    Fund alloted (revised) : Rs.0.01 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 100%
  • Project : New Coochbehar-Gumanihat (Cap.)
    Anticipated cost (2015-16) : Rs.23.75 Cr
    Cumulative Expenditure : Rs.23.75 Cr
    Fund alloted (2015-16) : Rs.49.98 Cr.
    Fund alloted (revised) : Rs.0.01 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 100%
  • Project : New Bangaigaon-Rangiya-Kamakhya (Cap.)
    Anticipated cost (2015-16) : Rs.1798 Cr
    Cumulative Expenditure : Rs.0 Cr
    Fund alloted (2015-16) : Rs.0 Cr.
    Fund alloted (revised) : Rs.0 Cr.
    Fund alloted (final) : Rs.0 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 0.00%
  • Project : Bongaigaon-Goalpara-Guwahati (176 KM) (Cap.)
    Anticipated cost (2015-16) : Rs.1831 Cr
    Cumulative Expenditure : Rs.0 Cr
    Fund alloted (2015-16) : Rs.0.01 Cr.
    Fund alloted (revised) : Rs.0.5 Cr.
    Fund alloted (final) : Rs.0 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 0.00%
  • Project : Digaru-Hojai (102 KM) (Cap)
    Anticipated cost (2015-16) : Rs.944.64 Cr
    Cumulative Expenditure : Rs.0 Cr
    Fund alloted (2015-16) : Rs.0.01 Cr.
    Fund alloted (revised) : Rs.0.5 Cr.
    Fund alloted (final) : Rs.0.01 Cr.
    Expenditure (2015-16) : Rs.0 Cr
    Financial progress during (2015-16) : 0.00%
    Overall financial progress : 0.00%
  • Project : Bogibeel Rail-cum-Road Bridge (Capital)
    Anticipated cost (2015-16) : Rs.4857.14 Cr
    Cumulative Expenditure : Rs.4090.78 Cr
    Fund alloted (2015-16) : Rs.701 Cr.
    Fund alloted (revised) : Rs.551 Cr.
    Fund alloted (final) : Rs.512.84 Cr.
    Expenditure (2015-16) : Rs.512.85 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 84.22%
  • Project : Harmuti-Naharlagun (Capital)
    Anticipated cost (2015-16) : Rs.406.4 Cr
    Cumulative Expenditure : Rs.511.46 Cr
    Fund alloted (2015-16) : Rs.30 Cr.
    Fund alloted (revised) : Rs.46 Cr.
    Fund alloted (final) : Rs.61.83 Cr.
    Expenditure (2015-16) : Rs.61.55 Cr
    Financial progress during (2015-16) : 99.55%
    Overall financial progress : 125.85%
  • Project : Jiribam - Imphal Road (Tupul) (Capital)
    Anticipated cost (2015-16) : Rs.4478.17 Cr
    Cumulative Expenditure : Rs.4927.33 Cr
    Fund alloted (2015-16) : Rs.1300 Cr.
    Fund alloted (revised) : Rs.1505 Cr.
    Fund alloted (final) : Rs.1541.8 Cr.
    Expenditure (2015-16) : Rs.1541.76 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 110.03%
  • Project : New Moynaguri - Jogighopa (Capital)
    Anticipated cost (2015-16) : Rs.2531.34 Cr
    Cumulative Expenditure : Rs.2225.98 Cr
    Fund alloted (2015-16) : Rs.378 Cr.
    Fund alloted (revised) : Rs.399.35 Cr.
    Fund alloted (final) : Rs.400 Cr.
    Expenditure (2015-16) : Rs.399.76 Cr
    Financial progress during (2015-16) : 99.94%
    Overall financial progress : 87.94%
  • Project : Araria - Galgalia (Capital)
    Anticipated cost (2015-16) : Rs.522.87 Cr
    Cumulative Expenditure : Rs.361.23 Cr
    Fund alloted (2015-16) : Rs.10 Cr.
    Fund alloted (revised) : Rs.110 Cr.
    Fund alloted (final) : Rs.306.31 Cr.
    Expenditure (2015-16) : Rs.306.32 Cr
    Financial progress during (2015-16) : 100%
    Overall financial progress : 69.09%
  • Project : Teteliya - Byrnihat (Capital)
    Anticipated cost (2015-16) : Rs.385.2 Cr
    Cumulative Expenditure : Rs.285.63 Cr
    Fund alloted (2015-16) : Rs.150 Cr.
    Fund alloted (revised) : Rs.85.35 Cr.
    Fund alloted (final) : Rs.46.14 Cr.
    Expenditure (2015-16) : Rs.46.14 Cr
    Financial progress during (2015-16) : 99.99%
    Overall financial progress : 74.15%
Daily Financial Review Statement ending 22-08-2016 (Approx.) FY 2016-17 uploaded............
Welcome to Accounts Department
N. F. Railway (Construction)

With an objective of the expansion of Railway network to facilitate socio-economic development of N. E. Region adjoining the seven sisters viz. Assam, Arunachal Pradesh, Nagaland, Mizoram, Meghalaya, Tripura and Manipur, as a part of Government policy, Construction Organization in N. F. Railway was set up in the year 1979 and since then this organization achieved many milestones and is striving hard for attaining the unfulfilled dreams and aspiration

Recent events and updates
FA & CAO/CON's Message

This web portal is launched with the aim of facilitating information on real time basis to our valued customers and is a small step in making Construction Accounts a paperless office

Quick Link
Copyright : 2014 | N.F.Rly (Con). ACCOUNTS DEPARTMENT | Disclaimer
Designed and Developed by Mr. Angshuman Sarma & Mr. Parag Moni Sarma.
Best viewed in 1024 x 768 resolution in Mozilla Firefox/Google Chrome or higher.